In What Order should I Renovate my House?

When planning a home addition or structural renovation in the Denver metro area, the process follows a specific sequence designed to address regional soil conditions and local building codes. Because our front range front range features expansive bentonite clay that can swell up to 10 percent in volume, starting with a stable foundation is the most critical phase.

We recommend following this order for your renovation project:

  1. Zoning and Site Evaluation: We begin by examining setback requirements and soil stability. A professional geotechnical assessment is essential here to determine how reactive soils will impact your design.
  2. Design and Structural Engineering: You must work with a licensed structural engineer to develop stamped structural drawings. These drawings are a mandatory requirement for obtaining permit approval in Colorado.
  3. Permitting: Plans are submitted to the local building department (such as the City and County of Denver). This stage typically takes four to eight weeks, so it is important to factor this duration into your overall timeline early.
  4. Foundation Work: This is the first phase of physical construction. Given Denver’s soil, we often utilize Helical Pier systems or reinforced concrete grade beams to ensure long-term stability against soil movement.
  5. Framing and Rough-ins: Once the foundation is secure, the project moves into framing, mechanical rough-ins, and interior finishing.

We also advise maintaining a 10 to 15 percent contingency budget throughout these steps to account for unexpected soil findings or weather-related schedule impacts. All estimates and quotes are preliminary and are not legally binding until confirmed in writing following an on-site inspection.